Permissions required for setting up a new Diesel Generator

Dear Environs,

Can any one help me out what are the permissions required for installing new D. G set in a hospital.
Is there any permissions need to be taken from Andhra Pradesh pollution Control board.
Since the Hospital already using one D.G Set.

Views: 1551

Reply to This

Replies to This Discussion

yes you need to aaply for varied consent to operate . 

and D.G set should be with canopy or an acoustic room  should be provided for a D.G set 

also their are parameters for the stack height of the exhaust of D.G set .

generally it should me more than 3m meters from roof level if D.G set's capacity is below 500kva i guess .

Dear,

Yes, you would require CTE (consent to establish) for new DG set installation ( capacity more than 15 KVA in case non industry.. but u need to confirm) & CTO (consent to operate)from the APPCB under Section 21 of the Air (Prevention & Control of Pollution) Act, 1981 as amended. 

For rest of the requirement check the below given link.

http://www.cpcb.nic.in/Generator.php

Thank you for the information sir

Both consent to operate and consent to operate is required from state board.Refer green book

Dr B N das

sir,
what is the green book. where can i get that.
thanking you sir

Reply to Discussion

RSS

Paryavaran.com -online webportal to network and do business and philanthropy with Indian Environment Organizations and Professionals


Notes

Network of Indian Environment Professionals LLC

Created by Chandra Kishore Feb 5, 2010 at 3:22pm. Last updated by Chandra Kishore Jan 20, 2020.

Notes Home

Created by Chandra Kishore Oct 5, 2009 at 3:19pm. Last updated by Chandra Kishore Apr 29, 2011.

© 2024   Created by Chandra Kishore.   Powered by

Badges  |  Report an Issue  |  Terms of Service