Dear Sirs,
Can any guide me regarding the change in Environmental Clearance Condition if CPP is changed to IPP.Only Supply of Coal is changed through Coal Linkage or e-auction or by both? Should i apply for fresh EC or old EC may be modified?

Views: 323

Reply to This

Replies to This Discussion

Dear Sir,

As per EIA notification-2006, there is provision for fresh EC in case of modification in technology. First page of the same is enclosed herewith for your ready reference.

regards,

Shiv

Attachments:

Dear Sir,

No change in technology is planned. Only CPP is being converted to IPP.

Well! then there is no need to obtain fresh EC.

Considering change in ownership and no change in fuel consumption i.e. coal quantity, I think you have to apply for EC-Amendment (Old EC) as well as new EC (if applicable), as your Captive Power Plant is been converted into Independent Power Producer.

All suggestions are welcome.

Reply to Discussion

RSS

Paryavaran.com -online webportal to network and do business and philanthropy with Indian Environment Organizations and Professionals


Notes

Network of Indian Environment Professionals LLC

Created by Chandra Kishore Feb 5, 2010 at 3:22pm. Last updated by Chandra Kishore Jan 20, 2020.

Notes Home

Created by Chandra Kishore Oct 5, 2009 at 3:19pm. Last updated by Chandra Kishore Apr 29, 2011.

© 2024   Created by Chandra Kishore.   Powered by

Badges  |  Report an Issue  |  Terms of Service