Kindly guide.

We have an existing crude oil pipeline passing through two diffrent states having consent for some "X" qty per anum.  However, we want to increase the pumping capacity to "Y" per anum.

 

As per the EIA notification, if the new pipeline is passing through sensitive areas then we require Environmental Clearance.

 

Please note that we have existing pipeline, and we want to increase the capacity of pipeline without doing any modification in pipeline.

 

My question is by doing amendment with state pollution control board will suffice our requirment or do we need to amend our environmnetal clearance also.

 

Please guide the same.

Thanks

Views: 338

Comment

You need to be a member of Indian Environment Network to add comments!

Join Indian Environment Network

Comment by GOPI KANTA GHOSH on July 31, 2014 at 6:45am

It has to be product and process specific

Comment by joshi on July 30, 2014 at 11:37pm
Still notification silent in this kind of scenario...... As per notification it's given applicability on different cases like as expansion, modification, increase in capacity.... ...My view you may refer to respective pollution control board for CCA ammendment and take advise from them...

There was a draft circular regarding EC 19/01/2009...in this circular it's mentioned.. If there is no increase in pollution load due to proposed change... Then PP has to give declaration regarding no increase in pollution load and exemption from EC.
After this no further circular regarding ec exemption...

For expansion.. Previous ec compliance report validated through regional office of MoEF is mandatory.. With out this they will not entertain our application as per circular of MoEF

Dear if you are going to increase pumping capacity ..then u have to identify indirect impact due to this change.... As its passing through sensitive area...... Need to think on various aspects.. Like.. Does your pipeline design capacity is more than proposed change....some time design capacity is not issue but physical condition is not good enough for increase in change... As its a matter of sensitive area...
Best suggestion is to consult your spcb for this and proceed further...
Comment by S.Das on July 29, 2014 at 10:00am

I think it is increase in quantity. Project proponent should inform MOEF and SPCB. You have to revise consent to operate also. In that case probably you have to amend your EC and CtO.

 

Comment by Dr S B Katoley on July 29, 2014 at 1:02am

Need some clarifications before I can give my comments.

Have you obtained EC previously?

Is the pipeline passing through sensitive areas?

Kindly revert back please.

Comment by BIJAYA NANDA DAS on July 28, 2014 at 11:25am

Amendment by S P CB will suffice,HOW ever SAFETY concerns may be adressed.

DR b n das

Comment by Rahul Singh on July 28, 2014 at 9:58am
The Environment notification does not consider the quantity of gas to be transported as prerequisite for granting the environment clearance.
Therefore in my opinion you need not to revise Environment Clearance.

In case of detail discussion and more clarification you can call on me on 9899101527.

Thanks
Rahul Singh

Paryavaran.com -online webportal to network and do business and philanthropy with Indian Environment Organizations and Professionals


Notes

Network of Indian Environment Professionals LLC

Created by Chandra Kishore Feb 5, 2010 at 3:22pm. Last updated by Chandra Kishore Jan 20, 2020.

Notes Home

Created by Chandra Kishore Oct 5, 2009 at 3:19pm. Last updated by Chandra Kishore Apr 29, 2011.

© 2024   Created by Chandra Kishore.   Powered by

Badges  |  Report an Issue  |  Terms of Service