As told in previous mails , ( My factory is new green field  factory , under construction and We have a Valid consent for Establishment ( COE) .
Please support with answer for the following queries .


1. When an industry can apply for hazardous waste authorisation ?

2. When an industry can get Hazardous waste authorisation ( Time frame between application and authorisation ) ?

3. Is there any linkage between Consent for operation and Hazardous waste authorisation

4. And Whether its possible to  get hazardous waste authorisation before getting Consent for operation..

I want do everything very perfectly in the right way ( 100 % Compliance with legal requirement )

   Regards

   Rajesh

   nature_ rajesh@yahoo.com

Views: 267

Comment

You need to be a member of Indian Environment Network to add comments!

Join Indian Environment Network

Comment by Sheetal Antil on July 15, 2012 at 1:38am

there is no fixed time frame for getting consent.. it may take from 4 to 6 months.

Yes. there is a linkage between hazardous application and Consent to operate. You have to submit Hazardous waste authorization with consent to operate, without HWM authorization application, Consent to operate will not be granted ( If ur industry is falling under hazardous waste generation category or producing Hazardous waste)

no, usually, hazardous waste authorization is granted with COnsent to operate. so you canot get it before.

Comment by Pravin M. Jadhav on July 13, 2012 at 7:04am
1. Industry can apply by filling Form 1 of Hazardous Waste (MHTB) Rules 2008 when industry is generating Hazardous waste as per Schedule I, II, III, V-A or V-B.
Either before starting the plant that is getting Consent to Establish or for Consent to Operate.

2. CFE along with authorisation will be issued by SPCB within 60 days from the application submission.
and For CFO along with aurthorisation will be issued within 60 to 90 days if there is no discrepancies in apllication.
3. Consent to Operate or Consent to Establish is as per Air Act 1981 and Water (PCP) Act and authorsiation is as per Hazardous Waste (MHTB) Rules 2008 under Envi Protection Act 1986.
4. Yes you can get it authoirastion along with CFE.
I would request you to kindly go through the following presentation this will definitely help you.

http://www.authorstream.com/Presentation/praveenmjadhav-333486-haza...


http://www.authorstream.com/Presentation/praveenmjadhav-333486-haza...

http://www.authorstream.com/Presentation/praveenmjadhav-333486-haza...
Comment by Sanjaya Kumar Mishra on July 11, 2012 at 10:57am

 

Dear Rajesh,

1. If you generate hazardous wastes as listed in the Schedule - I of Hazardous Wastes (Management, Handling and Transboundary Movement) Rules, 2008 and subsequent amendments; you are liable to obtain Authorization under the same rule. Practially, almost all projects during construction phase also generate hazardous wastes as listed in Schedule - I.

2. Time frame depends entirely upon the SPCB or PCC. However, if application is complete in all respect, you may be accorded authorization within 4 months.

3. There is a linkage between consent and authorization, in the way that operations from most of the factories or establishments generate HW.

4. Yes, you can.

 

But, most importantly, please do consult your local SPCB and PCC also.

 

All the very best for your willingness for 100% compliance.

 

Sanjay Mishra

http://www.ecomedia.co.in

Comment by Dipali on July 11, 2012 at 2:21am
Dear Rajeshbhai,
pl refere the HW Rules, 2008 (1) it is clear in defination of "authorisation" that authorisation means permission for generation...so you should possesse the authorisation before generation of HW. (2) As per Rule 5 (4), SPCB should decide the authorisation within 120 days from the date of application. (3 & 4) As SPCB in the Gujarat State has adopted common consents and authorisation (CC&A) concept, you have to apply for consents to operate in Water Act, Air Act and authorisation all together (if you plant is located within Gujarat).
Rgd
Comment by Balasaheb Sundarrao Deshmukh on July 11, 2012 at 12:22am

I am agree with Rajesh Sir, We are producing hazardous waste during construction phase also. please refer the Hazardous Waste Management handling Transboundry movement Rules 2008 Schedules. As per my knowledge no one is taking hazardous waste authorization during construction phase. Some SPCB time for application is six month, Two month, one month depends on that state pollution control board. Now a days every where facility of CHWTSDF is available for safe disposal. In some state we have to apply seperately for Hazardous waste authorization while many SPCb combine authorization in consent to operate. 

Comment by DASARI SRINIVASA RAO on July 10, 2012 at 11:57pm
only COE getting is not important but during operational and post operational management is necessary for proper environmental management methodologies
Comment by ganesan viswanathan on July 10, 2012 at 11:48pm

Dear Rajesh,

Even during construction phase,the project activity would generate haz waste such as Paint residue,containers,broken lights containing mercury,(from labour quarters) etc.Legally speaking the authorisation is required for construction phase also for the generation ,collection,storage and disposal.The authorisation is further required during operation phase along with the consent to operate.the time frame to get the authorisation normally one month.How ever u have to check with local SPCB.

Rgs

Ganesan

Comment by Dr.Dipendra Singha on July 10, 2012 at 11:20pm

There must be a point mentioned in the COE on this matter.

You can apply for HWA after getting the COE and before commissioning of your industry.

Generally took around 3-4 months. But it depends on the PCB. They will make a visit to your site to inspect and reaffirm the facilities mentioned in your application. After this PCB will give u the authorization. 

Comment by aakash Verma on July 10, 2012 at 2:25pm

Dear,

1. If U (Industry) are generating Haz. waste (as per MSIHC, 1989), then u hav to for authorisation. for more details contact concern PCB.

 

Comment by SACHIN S PANDEY on July 10, 2012 at 11:23am

1. In your consent, it will mention , how much of hazardous waste u are permitted?

Paryavaran.com -online webportal to network and do business and philanthropy with Indian Environment Organizations and Professionals


Notes

Network of Indian Environment Professionals LLC

Created by Chandra Kishore Feb 5, 2010 at 3:22pm. Last updated by Chandra Kishore Jan 20, 2020.

Notes Home

Created by Chandra Kishore Oct 5, 2009 at 3:19pm. Last updated by Chandra Kishore Apr 29, 2011.

© 2025   Created by Chandra Kishore.   Powered by

Badges  |  Report an Issue  |  Terms of Service