As told in previous mails , ( My factory is new green field factory , under construction and We have a Valid consent for Establishment ( COE) .
Please support with answer for the following queries .
1. When an industry can apply for hazardous waste authorisation ?
2. When an industry can get Hazardous waste authorisation ( Time frame between application and authorisation ) ?
3. Is there any linkage between Consent for operation and Hazardous waste authorisation
4. And Whether its possible to get hazardous waste authorisation before getting Consent for operation..
I want do everything very perfectly in the right way ( 100 % Compliance with legal requirement )
Regards
Rajesh
nature_ rajesh@yahoo.com
Comment
there is no fixed time frame for getting consent.. it may take from 4 to 6 months.
Yes. there is a linkage between hazardous application and Consent to operate. You have to submit Hazardous waste authorization with consent to operate, without HWM authorization application, Consent to operate will not be granted ( If ur industry is falling under hazardous waste generation category or producing Hazardous waste)
no, usually, hazardous waste authorization is granted with COnsent to operate. so you canot get it before.
Dear Rajesh,
1. If you generate hazardous wastes as listed in the Schedule - I of Hazardous Wastes (Management, Handling and Transboundary Movement) Rules, 2008 and subsequent amendments; you are liable to obtain Authorization under the same rule. Practially, almost all projects during construction phase also generate hazardous wastes as listed in Schedule - I.
2. Time frame depends entirely upon the SPCB or PCC. However, if application is complete in all respect, you may be accorded authorization within 4 months.
3. There is a linkage between consent and authorization, in the way that operations from most of the factories or establishments generate HW.
4. Yes, you can.
But, most importantly, please do consult your local SPCB and PCC also.
All the very best for your willingness for 100% compliance.
Sanjay Mishra
I am agree with Rajesh Sir, We are producing hazardous waste during construction phase also. please refer the Hazardous Waste Management handling Transboundry movement Rules 2008 Schedules. As per my knowledge no one is taking hazardous waste authorization during construction phase. Some SPCB time for application is six month, Two month, one month depends on that state pollution control board. Now a days every where facility of CHWTSDF is available for safe disposal. In some state we have to apply seperately for Hazardous waste authorization while many SPCb combine authorization in consent to operate.
Dear Rajesh,
Even during construction phase,the project activity would generate haz waste such as Paint residue,containers,broken lights containing mercury,(from labour quarters) etc.Legally speaking the authorisation is required for construction phase also for the generation ,collection,storage and disposal.The authorisation is further required during operation phase along with the consent to operate.the time frame to get the authorisation normally one month.How ever u have to check with local SPCB.
Rgs
Ganesan
There must be a point mentioned in the COE on this matter.
You can apply for HWA after getting the COE and before commissioning of your industry.
Generally took around 3-4 months. But it depends on the PCB. They will make a visit to your site to inspect and reaffirm the facilities mentioned in your application. After this PCB will give u the authorization.
Dear,
1. If U (Industry) are generating Haz. waste (as per MSIHC, 1989), then u hav to for authorisation. for more details contact concern PCB.
1. In your consent, it will mention , how much of hazardous waste u are permitted?
Paryavaran.com -online webportal to network and do business and philanthropy with Indian Environment Organizations and Professionals
Join us as Institutional Member today
Organizations where our Members Come from: More than 2000 at the last count...
_______________
Organica Biotech joins us as a Diamond Institutional Member. Check Here
LEAD INDIA joins us as Diamond Institutional member. Check here
_______________
ERM joins as Partner. Invites you as India Business Partner
Envitrans Infosolutions Pvt. Ltd.
--------------------
Created by Chandra Kishore Feb 5, 2010 at 3:22pm. Last updated by Chandra Kishore Jan 20, 2020.
Created by Chandra Kishore Oct 5, 2009 at 3:19pm. Last updated by Chandra Kishore Apr 29, 2011.
© 2025 Created by Chandra Kishore. Powered by
You need to be a member of Indian Environment Network to add comments!
Join Indian Environment Network