As en Environment Officer what are the steps for establishing new cement plant in rajasthan where there is no any sensitive issue except ground water abstraction. please guide me. 

Views: 82

Reply to This

Replies to This Discussion

Dear Mr. Ashish,

Please mention your capacity of cement plant.

1) If plant capacity (production capacity) is > or equal to 1.0 million tonnes/annum, that project is falls under Category "A" as per EIA Notification & Require to take Environmental Clearance (EC) from Ministry of Environment & Forests (MoEF), Delhi.
2) If plant capacity (production capacity) is < 1.0 million tonnes/annum, that project is falls under Category "B" & Require to take EC from MoEF.

3) Project location should not fall with in 10 Km of any Protected Areas & Eco-sensitive areas etc, If project falls with in 10 Km radius (if there is no declared Eco-sensitive Zone around NP/WLS/PA), then you have to take NBWL clearance.

To get EC, Major issues may as follow:
1) To conduct Public Hearing
2) To take approval for GW abstraction from CGWA.

Dear sir,

Thank you very much.

Plant capacity is around 3.0 million tonnes/annum but region is in notified area decided by CGWA then from where we can fullfill our water requirment.



Gopi Krushna N said:

Dear Mr. Ashish,

Please mention your capacity of cement plant.

1) If plant capacity (production capacity) is > or equal to 1.0 million tonnes/annum, that project is falls under Category "A" as per EIA Notification & Require to take Environmental Clearance (EC) from Ministry of Environment & Forests (MoEF), Delhi.
2) If plant capacity (production capacity) is < 1.0 million tonnes/annum, that project is falls under Category "B" & Require to take EC from MoEF.

3) Project location should not fall with in 10 Km of any Protected Areas & Eco-sensitive areas etc, If project falls with in 10 Km radius (if there is no declared Eco-sensitive Zone around NP/WLS/PA), then you have to take NBWL clearance.

To get EC, Major issues may as follow:
1) To conduct Public Hearing
2) To take approval for GW abstraction from CGWA.

Reply to Discussion

RSS

Paryavaran.com -online webportal to network and do business and philanthropy with Indian Environment Organizations and Professionals


Notes

Network of Indian Environment Professionals LLC

Created by Chandra Kishore Feb 5, 2010 at 3:22pm. Last updated by Chandra Kishore Jan 20, 2020.

Notes Home

Created by Chandra Kishore Oct 5, 2009 at 3:19pm. Last updated by Chandra Kishore Apr 29, 2011.

© 2024   Created by Chandra Kishore.   Powered by

Badges  |  Report an Issue  |  Terms of Service